    Lydian's 150 MW/600 MWh Faraday battery in Utah enters operation, contracted to support Meta data center

    Lydian Energy said its 150 MW/600 MWh Faraday battery energy storage system in Utah County, Utah, has been in commercial operation since Sept. 18, supplying contracted capacity to PacifiCorp under a long-term agreement. The four-hour LFP system is also contracted under Rocky Mountain Power's Schedule 34 tariff in support of Meta's Eagle Mountain data center. It sits next to the 525 MW Faraday solar plant, sharing its substation, and was built in about 10 months. A second battery, Faraday BESS 2, is in development.