What we know
Where sources disagree
Comparison with Michigan's electricity consumption
- The 403 data centers used more electricity than the state of Michigan. — Slashdot, Hacker News
- The data centers used nearly as much as Michigan, or more than 80% of the 99 TWh Michigan sold in 2024. — Tom's Hardware, Latitude Media
Increase in emissions versus earlier estimates
- Emissions are three times higher than before the AI boom. — Slashdot
- Emissions are two to three times a 2018 peer-reviewed estimate. — Tom's Hardware, Latitude Media
Confirmed by several sources
- A Harvard-led study published in Nature Sustainability analyzed US hyperscale data centers' electricity use and emissions. — Tom's Hardware, Slashdot, The Verge, Latitude Media
- The study covered 403 hyperscale data centers, narrowed from 675 candidate sites, with an average capacity of about 40 MW. — Tom's Hardware, Slashdot, Ars Technica
- The data centers used about 82 TWh of electricity in a year, about 1.8% of the US total. — Tom's Hardware, Latitude Media
- The study period ran from May 2024 through April 2025. — Ars Technica, Latitude Media
- The facilities emitted an estimated 25.7 million metric tons of CO2. — Tom's Hardware, Latitude Media
- More than half of the electricity came from fossil fuel sources. — Tom's Hardware, Slashdot, The Verge, Latitude Media
- Data center electricity draw is not officially tracked separately, so usage was estimated from capacity. — Tom's Hardware, Slashdot
- The study could not distinguish AI workloads from other data services. — Slashdot, Ars Technica
Reported by one source
- Fossil fuels supplied 54% of the energy, and most use was concentrated in Iowa, Ohio, Oregon and Virginia. — Latitude Media
- The data centers' CO2 output is on par with Denmark's annual emissions. — Latitude Media
- Candidate sites came from data vendor Baxtel, and emissions were estimated using EPA average mixes across 23 grid regions. — Tom's Hardware
- The estimate excludes facilities powered by off-grid gas plants. — Hacker News
- Hyperscale data centers likely use more electricity than many countries. — The Verge
Open questions
- It is not clear how much of the measured electricity use is attributable to AI workloads. — Slashdot, Ars Technica
- Actual grid draw remains unknown because figures are modeled from capacity and estimated utilization rather than metered data. — Tom's Hardware
Coverage 8 publishers
TechmemeFirst report
Just 400 US Data Centers Use More Electricity Than Michigan
New Harvard research shows that data-center power demand is outstripping states—and that doesn’t even include facilities with off-grid gas plants.
-
Just 400 US Data Centers Use More Electricity Than Michigan
New Harvard research shows that data-center power demand is outstripping states—and that doesn’t even include facilities with off-grid gas plants.
-
Just 400 US Data Centers Use More Electricity Than Michigan
New Harvard research shows that data-center power demand is outstripping states—and that doesn’t even include facilities with off-grid gas plants.
-
Study: Hyperscale data centers now use nearly as much power as Michigan
A new study of U.S. data centers found that hyperscale data centers use nearly as much electricity in a year as the entire state of Michigan — and that the total carbon dioxide they release is on par with Denmark’s emissions in a year.…
-
US data centers now burn more electricity than a midsized country
Fossil fuels are still the biggest source of electricity for hyperscale data centers in the US, a new paper published in the journal Nature Sustainability shows. They likely burn through more electricity collectively than many countries do…
-
Hyperscale data centers use 2% of US electricity
One flashpoint for the tech industry’s all-in push on large language models has been the sudden rush to turn investment money into hyperscale data centers. The rush hasn’t allowed anyone to plan how to supply the required electricity…
-
Just 400 US Data Centers Use More Electricity Than Michigan
An anonymous reader quotes a report from Wired: Just 400 hyperscale data centers connected in the US used as much electricity as the state of Michigan in a single year, new Harvard research has found. The study, published Monday in Nature…
-
A Harvard-led study estimates that 403 hyperscale U.S. data center sites consumed about 82 TWh of electricity in a year, 1.8% of the country’s total, with more than half coming from gas and coal sources, Wired reports. This compares to the…
Earliest report first. Articles stay on their publishers’ sites; each link opens the original.