APA Group moves ahead with Sybella Creek solar farm and 104 MWh battery near Mount Isa

APA Group is advancing the Sybella Creek project near Mount Isa, Queensland: a 72 MW solar farm plus a 52 MW/104 MWh battery, costing AUD 259 million. Accounts differ on timing: one says APA reached a final investment decision with construction due later this year and completion in mid-2028, while another says construction has officially begun. The project serves Ernest Henry Mining under a long-term energy supply agreement and will be the first large-scale battery on the North West Power System.

AI-written summary, checked against the cited sources. How summaries work

Image: pv magazine Australia

What we know

Where sources disagree

Construction status

  • APA reached a final investment decision and construction is set to begin later this year. — ESS News
  • Construction has officially commenced. — pv magazine Australia

US dollar value of the AUD 259 million investment

Confirmed by several sources

  • The project comprises a 72 MW solar farm and a 52 MW/104 MWh battery energy storage system near Mount Isa, Queensland. — ESS News, pv magazine Australia
  • The project budget is AUD 259 million. — ESS News, pv magazine Australia
  • APA is developing the project under an energy supply agreement with Ernest Henry Mining, a wholly owned subsidiary of Evolution Mining operating a copper-gold-silver mine. — ESS News, pv magazine Australia
  • The battery is intended to improve reliability for the North West Power System, which serves mining customers and local communities. — ESS News, pv magazine Australia

Reported by one source

  • Project completion is scheduled for mid-2028. — ESS News
  • The energy supply agreement runs until mid-2046 and supports the gas-powered Diamantina Power Facility, which will provide firming capacity. — ESS News
  • It will be the first large-scale battery energy storage system in the North West Power System. — pv magazine Australia
  • The project sits beside APA's 88 MW Dugald River Solar Farm and will share its switchyard, ancillary buildings and maintenance facility. — pv magazine Australia

Open questions

Coverage 2 publishers

  1. pv magazine AustraliaFirst report

    APA begins solar and battery build in Queensland’s northwest

    APA Group, Australia’s largest listed gas infrastructure owner and operator, announced that construction has officially commenced on the $259 million (USD 171.6 million) Sybella Creek solar farm and battery project being built near Mount…

  2. ESS News

    APA advances 104 MWh battery project in Australia

    Australian energy infrastructure company APA Group is set to build, own and operate a large-scale solar project and battery energy storage system (BESS) in Queensland, Australia. The company said it has reached a final investment decision…