Project capacity
- The project is 509 MW. — pv magazine USA, Solar Power World
- The project headline says 450 MW, while its summary describes a 420 MW hybrid park. — PV Tech
Confirmed by several sources
- ContourGlobal has begun construction of a solar-plus-storage project in Arizona. — pv magazine USA, PV Tech, Solar Power World
- Tesla is identified as the purchaser under a power purchase agreement. — pv magazine USA, Solar Power World
Reported by one source
- The project includes 1.4 GWh of storage. — Solar Power World
- The project is expected to be completed in 2028. — PV Tech
- The project is expected to supply more than 1 TWh of clean electricity annually under a long-term agreement. — pv magazine USA
Coverage 3 publishers
Solar Power WorldFirst report
Solar + storage construction starts on Project Sterling in Arizona
Solar and storage system construction has begun for Project Sterling in Mohave County, Arizona. ContourGlobal is building the 509-MW solar and 1.4-GWh storage project, for which Tesla has already signed a PPA. “Arizona’s sun has been…
-
ContourGlobal breaks ground on 450MW solar-plus-storage facility in Arizona
The IPP has begun the build phase of a new 420MW hybrid renewable energy park in Mohave County, Arizona, with completion due in 2028.
-
ContourGlobal breaks ground on 509 MW solar-plus-storage project in Arizona
The developer will supply more than 1 TWh of clean electricity annually to Tesla under a long-term corporate power purchase agreement.